Crozet Library Nearly Finished, Streetscaping Underway, North Sidewalk Soon

It’s amazing what one can learn when one pays attention to what the Board of Supervisors discuss … particularly when Charlottesville Tomorrow points out that the Board is discussing such matters.

The Office of Facilities Development Capital Projects Status Report pdf is here.

In summary:

– Crozet Library should be complete in August

– Crozet Streetscape Phase II has all of the rights of way and utility dedications – plan for 14 months construction

– Crozet North Sidewalk – Bid and award in 3rd Quarter 2013 – plan for 3 months construction

– Crozet Parks’ roads will be resurfaced this year

Dig in. Get informed.

Office of Facilities Development (OFD)
Capital Projects Status Report
2
nd Quarter CY 2013
(I’m saving the pdf here as well … sometimes my sites seem to be more dependable than others’ 🙂 )

Print Friendly, PDF & Email

Something to say?