Streetscape Coming to a Close Soon

Written by

Crozet Streetscape - 25 October 2014

Today’s Crozet Streetscape update, via email:

The following progress was made last week:
  • All remaining crosswalks were completed.
  • All remaining mulching was completed.
The following items are scheduled through the end of the project:
  • Final striping and signage installation are scheduled for tomorrow and Wednesday.
  • A Substantial Completion inspection will be held with VDOT the first week of November.
  • Substantial Completion is officially November 18th and Final Completion is December 18th.
For more information on the Crozet Streetscape project, visit www.albemarle.org/crozetstreetscape.

 

I hear they’re going to do a grand opening/ribbon cutting party …

 


    Comments

    2 responses to “Streetscape Coming to a Close Soon”

    1. Matt Avatar
      Matt

      Overall, big improvements. However, I have a couple criticisms:
      -natural stone should have been incorporated into the retaining wall and crosswalks,
      -the speed limit on Jarman’s Gap should be raised to 35mph,
      -Oak trees should be planted,
      – the stop light at The Square should be replaced so it matches the new street lamps and so you can see it when you’re actually stopped.

    2. […] The Streetscape came close to finishing […]

    Something to say?