Today’s Crozet Streetscape update, via email: The following progress was made last week: All remaining crosswalks were completed. All remaining mulching was completed. The following items are scheduled through the end of the project: Final striping and signage installation are scheduled for tomorrow and Wednesday. …
Streetscape Update – 9 October 2014
Via email – The following progress was made this week: • Approximately 7½ of the 12 total number of crosswalks are installed. • Several crosswalk base slabs were poured too high. The contractor demolished and replaced a portion of these at 3 locations and will …
Streetscape Update – 4 October 2014
via email: (Personally, I’d be Ok with no striping – it’s cleaner 🙂 ) The following progress was made this week: Pavers for approximately 3-1/2 of the 12 total crosswalks (!) (italics & ! added by me – jd) were installed. Several crosswalk base slabs were …
Streetscape Update – 22 September 2014
Update 24 September with a few photos taken this morning: Despite it seeming as if little has been happening, we’re awfully close to the finish … via email: Traffic Notice Final asphalt installation will proceed this week with the following schedule: • Tuesday, September …
Streetscape Update 12 September 2014
via email:
Traffic Notice:
Please be aware of the temporary “bumps” at each crosswalk. “Bump Ahead” signs have been posted to warn motorists of the changing road conditions. Please drive slowly, remain alert and drive/walk carefully when traveling through the construction zone. Thank you for your patience and courtesy to motorists, pedestrians, and workers during this difficult phase of construction.
Crozet Streetscape Construction Updates:
The following progress was made last week:
Steetscape Update 30 August 2014 – Crosswalks & Native Plants
via email: PROJECT UPDATE: TRAFFIC NOTICE: Please note that we are in the process of installing crosswalks, which requires the installation of temporary “bumps” at each crosswalk. “Bump Ahead” signs have been posted to warn motoristsof the changing road conditions. Please drive slowly over …
Streetscape Update – 26 August 2014
via email: As previously advised, crosswalk installation across Crozet Avenue and Jarmans Gap Road started this week. This work requires the use of steel plates to cover the newly poured base slabs until the slabs cure in approximately one day. After the concrete cures the …
Streetscape Update 24 August 2014
via email: The following progress was made over the past two weeks: • Installation of the remaining paver sidewalks. • Wall installation at Morningside. • Curb and sidewalk at The Square intersection. • Base paving of the Library Avenue extension. • Hand railing on the …
Streetscape Update – 18 July 2014
Crozet streetscape this morning. pic.twitter.com/5p9dahpPUG — realcrozetva (@realcrozetva) July 16, 2014 via email:
Crozet Streetscape Update – 11 July 2014
via email –