Crozet’s Water Pump Station Coming Online Today

 

 

1 – if your water becomes discolored, run the water.

2 – Context on Crozet’s water projects at Crozet Gazette (bolding mine)

Currently, there are two sets of water system improvements underway: (1) three ongoing projects at the Crozet Water Treatment Plant (WTP), and (2) three interrelated projects at the Beaver Creek Dam. Upgrades to the WTP on Rt. 240, first described in detail here in February, have progressed according to schedule. Those upgrades include the installation of granular activated carbon filters for cleaner water, now operational, at a cost of $3.4 million, and the construction of a new finished water pump station, now 90 percent complete and expected to be online by September, at a cost of $2.6 million.

Print Friendly, PDF & Email

One Reply to “Crozet’s Water Pump Station Coming Online Today”

Something to say?