Infrastructure is expensive.
There’s always a lot happening in Crozet; I’m writing these as much for you as for me — my clients expect me to know my market, and this is part of my ongoing research. *
*Framework and sourcing provided by Claude; edited and vetted by me.
Top line: The new Beaver Creek pump station is out to bid, with construction set to start in May 2027. Work on the dam and Browns Gap Turnpike won’t start until 2030.
1. Update: Beaver Creek pump station is out to bid; dam work pushed to 2030–2032
Earlier this month I passed along the Crozet Gazette’s report on the new Beaver Creek pump station. The Rivanna Water and Sewer Authority’s own Nov. 17 board packet now fills in the dates. Construction bids for the pump station, intake, and pipe to the Crozet water plant on Route 240 have been advertised. RWSA staff expect to recommend a contractor in January. The packet lists construction from May 2027 to December 2029 and a $39 million budget. The dam spillway work, which includes rebuilding Browns Gap Turnpike where it crosses the dam, is a separate $33.5 million project. RWSA expects a $20 million federal grant for it. That work is scheduled from January 2030 to December 2032, a year later than the end-of-2031 date the Gazette reported.
I’m curious to see how they do this. It’s going to fascinating to watch, and likely a bit frustrating to experience.
Sources: RWSA board packet, Nov. 17, 2026 (PDF); Crozet Gazette, Nov. 6
2. Other Crozet water work underway
The same packet shows two other Crozet projects already under construction. The first is a $13.2 million expansion of the activated-carbon treatment at the Crozet water plant, 45% complete with completion in May 2028. The second is a $12.35 million rehab of Crozet’s water pump stations, 35% complete with completion in December 2027. An update to the Crozet Drinking Water Infrastructure Plan is nearly finished and goes to the RWSA board in December. — Next meeting is 15 December at 2:15pm
Source: RWSA board packet, Nov. 17, 2026 (PDF)
Why this stuff matters for Crozet buyers/sellers/neighbors
- The pump station has moved from plans to bids. If you live near the Beaver Creek dam or along the pipe route to Route 240, we can expect construction activity starting around May 2027.
- Browns Gap Turnpike over the dam won’t be rebuilt until 2030–2032. That’s later than first reported, and dates like these tend to slip.
- More water capacity doesn’t approve any new homes. That still happens one rezoning at a time. The December infrastructure plan update is the one to read for how much growth the system is being planned for.